GILLAN CHERYL NEWCheryl Gillan is the Member of Parliament for Chesham and Amersham. Follow Cheryl on Twitter.

Today’s National
Audit Office report into High Speed 2
will set off alarm bells all across Government
and should bring about a major rethink of the Government’s transport policy.

The 50-page report
was understatedly damning of the preparation for HS2, exposing fundamental
flaws in the project and the project team. It confirmed that Government had failed
to set out clear and cohesive strategic objectives and, more worryingly,
highlighted the serious doubts over the ability and capacity of both the
Department of Transport and its subsidiary company, HS2 Ltd, to successfully
deliver the project.

The NAO judged
the timetable to be overly ambitious and it has already resulted in mistakes
being made by the Department on the benefit-cost calculations. The intention to
introduce a Hybrid Bill in October 2013 seems now to be impossible and, therefore, it will likewise be impossible that this legislation will be passed
before the next General Election. Over ambitious timetabling was also one of
the contributory factors to the failure of the West Coast Mainline franchise and
it would appear that the Department of Transport has failed to learn from its
mistakes.

The Department
comes under criticism for failure to engage adequately with stakeholders and it
would even appear that it is failing to address criticisms from its own
internal auditors. It is claimed that there
are more than just a few problems with finding enough staff of the right
calibre to give people the confidence that this project will be well
implemented.


Those alarm
bells should also be ringing in the Treasury. On current assumptions the
project will require more money than the Department currently has allocated and
already a £3.3 billion funding gap for Phase 1 has been identified. Furthermore, such is the level of incompetence
it is not clear whether the Government will need to pay VAT on top of the current
cost for the project and, if it is necessary, it has not been included in the
calculations to date. Along with the extra £8.15 billion needed for rolling
stock, the cost of this project is already spiraling out of control. This
project looks to be turning into a money-gobbling monster and if the small,
seemingly innocuous Preparation Bill goes through before the Summer, the Depart,emt
of Transport will indeed have a license to print money at the expense of all
the other Departments who are squealing under the Chancellor’s vice-like grip
on the country’s finances.

The preparation
has been poor across the board and the NAO report casts doubt over whether the
Government has done the necessary research into how exactly this project will
bring the benefits that have been espoused by Ministers. There can be no
rebalancing of the economy for at least 20 years as the proposed legislation in
the Hybrid Bill only deals with the Southern link from London to Birmingham. It
is the Northern Y-section that would bring the benefits of rebalancing but they
will not be apparent for decades.

What the project
will do is relieve a bit of the commuter traffic, so effectively HS2 could be
seen as a highly expensive way to deal with commuter traffic into London. I do
not think the country can afford a project that obviously will not even deliver
any so called rebalancing of the economy until Phase 2, North of Birmingham, is
built, which will not happen for at least 20 years. That of course
will mean London and the South East will ironically become more attractive,
creating a wider gap between North and South for any rebalancing to address.

The Major Projects
Authority has looked into the project three times already, but Government will
not publish their findings. However, from the NAO report’s reference to those
reviews it is revealed that they have identified concerns around confidence in
delivery of the project, the risky timetable, skills capability and resources
and affordability.

All in all, this
report calls into question both the principles and basis of HS2 and whether the
Department and HS2 Ltd are fit to deliver it. If it proceeds the Government
will lock the country into a project which will dominate all spending on
transport for many years to come without delivering the outcomes claimed for it
with any degree of believable certainty. I now call upon
my colleagues in Government to halt this project, reassess the country’s
transport requirements and replace HS2 with a more realistic set of proposals
which can be delivered effectively and efficiently rather than taking this high-risk project any further.